Help with Micrsoft Project

  suburban train 18:50 03 Nov 05
Locked

HI All

I have a problem I am trying to show a task that starts the 01 Nov and finishes 01 dec this year.

The task should only take 10 hours to complete but I may be working on this task a couple of hours of the day or some days none at all.

How can I reflect this, everytime I try to change the duration it changes the dates, if I change the dates then the hours jump to something high like 150 hours.

How can i get round this.

So basically I want to show a task starts the 01 Nov and finishes 01 dec this year but will only 10 hours to complete.

  suburban train 20:07 03 Nov 05

^

  suburban train 22:03 03 Nov 05

can anyone help?

  diy 22:27 03 Nov 05

try reducing the rescource units in task information ie less than 100%

This thread is now locked and can not be replied to.

Nintendo Switch review: Hands-on with the intuitive modular console and its disappointing games…

1995-2015: How technology has changed the world in 20 years

Prehistoric Britain is laid out in these Royal Mail stamp illustrations

Best running headphones | Best sport & fitness headphones: 4 brilliant pairs of wireless…